Wednesday, 11 February 2009
Subscribe to:
Post Comments (Atom)
 
Nov 2009
17th- concreting began out the back
3rd  - pool coping, Fence ( pool and one side) and block wall all finished
Oct 2009
7th - the pool began 
Aug 2009
15th  - We moved in
14th - Hand over
10th - sentinal installed Music hub, ducted Vac, phone points alarms Ect 
6th - Oven, dishwasher, cook top, range hood installed 
July 2009
25th - Front received a new coat of applied finish
23rd - We met with Mr L our new Site supervisor. 
17th - Electrical fit off, shower screens and mirrors installed 
14th - Steps poured 
10th -Internal painting finished, concrete for porch slab formed up
6th - Internal paining commenced
4th  - Cornice FINALLY started & kitchen bulk heads installed.
1st  -iron work erected. 
June 2009
20th  - Tiles started 
18th  -The Kitchen installed.
16th  - The fixing chippies started and tilers start 
12th  - Real stair case installed
11th  - temporary stair case removed
8th  - Dry wall completed
4th - Dry wall started
3rd  - Insulation installed 
May 2009
21st - Tilers and guttering finished
19th  - Air con, Sound and visual, ducted vac, and alarm installed
15th  - Electrical started
6th  - Rendering 1/2 painted.
April 2009
29th - sarking laid for roof tiles
21st  - Fascia and Gutter arrived
17th - Rendering finished
15th  - Rendering began
4th - Brick inspection with SS
March 2009
27th March - Kookaburra pools go bust
16th March - Plumbing started
5th March - Scaffolding is erected
2nd March - Brick work continues
February 2009
28th  - We sign the contract for Narellan Pools
27th  - More brick laying
25th  - Brickies begin laying bricks
18th  - BRICKS ARRIVE!
13th  - Safety stairs installed in side
11th  - Goodies for brick laying arrives
10th  - Frame Completed.
9th    - Windows put in.
5th     - Frame started.
1st - Storm water and surface drainage complete.
January 2009
31st - Plumbing finished
30th  - Frames Delivered and Plumbing continued.
28th  - Progress payment #1 PAID!
23rd - Slab Poured.
22nd -Site prep finished.
20th  - Steal Delivered.
19th  - Waffle Pods delivered.
17th  - Slab formed and plumbing started.
13th - Site works resume.
1st   - We moved for the second time .
December 2008
20th  - We Met our SS Mark.
13th - surveyor returns and repegs site.
8th - Site establishment.
11th - Site excavation.
November 2008
7th  - Our file handed over to the Construction Planning and Programming department.
5th  - Building agreement SIGNED!
October 2008
4th  - Peg survey done.
September 2008
25th  - DA approved.
12th  -Studio M visit to choose our goodies for the house
July 2008 2008
29th  - Plans go to council.
18th  - Tender C delivered
17th   - Soil tests taken
6th  - Wendy from head office contacted us.
June 2008
30th  - Met Bob and Renaye at Goulburn and chose the Regent Grande.
May 2008
14th  - Beechwood goes bust!.
April 2008
12th  - We moved to Yass
24th  - Settlement day of Gungahlin house.
29th  - Neighbour consultation ended.
March 2008
7th  - Told by Beechwood we were off to council
September 2007
23rd  - Markings for Beechwood house on land
19th  - Exchanged on Land
14th  - Our Gungahlin house is on the market!
August 2007
 25th   - We Bought our land!