Thursday, 15 January 2009
What's Next? The schedule explains...
Spoke with Mark (my Project Manager) yesterday afternoon, here is the updated schedule:
Monday, 19th January 2009 - Formwork for the concrete slab commences.
Tuesday, 20th January 2009 - Slab preparation activities (waffle pods, steel mesh, drainage).
Wednesday, 21st January 2009 - Slab preparation activities (waffle pods, steel mesh, drainage).
Thursday, 22nd January 2009 - Slab pour for main house, garages and the water tanks.
Friday, 23rd January 2009 - Completion of slab pour activities (if required).
Monday, 26th January 2009 - Australia Day Holiday
Tuesday, 27th January 2009 - Delivery of timber frames, roof trusses and windows.
I assume the framing contractors will arrive shortly thereafter.
John & Tarin.
Monday, 19th January 2009 - Formwork for the concrete slab commences.
Tuesday, 20th January 2009 - Slab preparation activities (waffle pods, steel mesh, drainage).
Wednesday, 21st January 2009 - Slab preparation activities (waffle pods, steel mesh, drainage).
Thursday, 22nd January 2009 - Slab pour for main house, garages and the water tanks.
Friday, 23rd January 2009 - Completion of slab pour activities (if required).
Monday, 26th January 2009 - Australia Day Holiday
Tuesday, 27th January 2009 - Delivery of timber frames, roof trusses and windows.
I assume the framing contractors will arrive shortly thereafter.
John & Tarin.