Wednesday, 28 January 2009

Building Schedule Updates...

Hi everyone,

I spoke with Mark, my Project Manager this morning and we have some updates to the building schedule.

Tomorrow, Thursday, 29th January 2009 - The Drainer will go in with his equipment and do all the external sewerage and drainage pipework.

Friday, 30th January 2009 - The frames and windows are scheduled to arrive. This was changed from last Tuesday as the Drainer hadn't done what he needed to do prior to the arrival of the frames and windows.

Wonder when the carpenters will start on the frame!

No comments: