The Steel Mesh Has Landed...
The steel mesh has arrived, now the concretors have everything they need to prepare the slab for pouring later this week (probably Thursday or Friday).
On site we now have:
- Waffle Pods,
- Steel reinforcement bars,
- Steel mesh stirrups,
- AND of course the Steel Mesh.
So tomorrow, weather permitting (not looking good at present), is planned to be the slab preparation i.e setting up the waffle pods and the rest of the formwork, deep edge beam formation and setting up the steel mesh over the pods.