Friday, 24 July 2009
PCI still not clear yet...
This morning we heard from Mr L. This is the schedule for the coming week:
Today, 24th - The plumber will be in to do his fit off (he never completes his work, let's see if he does today),
Monday, 27th - Excavator to arrive - to remove the excess spoil from the front and rear yards and to cut the rear area behind the garage.
Tuesday, 28th - Fitoff carpenter to arrive and complete his work (door handles, fix some architraves) and hopefully the air con contractor will arrive to install the air con unit.
Wed & Thu - not sure yet
Friday, 31st - Installation of panelift doors and roller door.
That's it for now...
John & Tarin
Today, 24th - The plumber will be in to do his fit off (he never completes his work, let's see if he does today),
Monday, 27th - Excavator to arrive - to remove the excess spoil from the front and rear yards and to cut the rear area behind the garage.
Tuesday, 28th - Fitoff carpenter to arrive and complete his work (door handles, fix some architraves) and hopefully the air con contractor will arrive to install the air con unit.
Wed & Thu - not sure yet
Friday, 31st - Installation of panelift doors and roller door.
That's it for now...
John & Tarin
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment