Nov 2009
17th- concreting began out the back
3rd - pool coping, Fence ( pool and one side) and block wall all finished
Oct 2009
7th - the pool began
Aug 2009
15th - We moved in
14th - Hand over
10th - sentinal installed Music hub, ducted Vac, phone points alarms Ect
6th - Oven, dishwasher, cook top, range hood installed
July 2009
25th - Front received a new coat of applied finish
23rd - We met with Mr L our new Site supervisor.
17th - Electrical fit off, shower screens and mirrors installed
14th - Steps poured
10th -Internal painting finished, concrete for porch slab formed up
6th - Internal paining commenced
4th - Cornice FINALLY started & kitchen bulk heads installed.
1st -iron work erected.
June 2009
20th - Tiles started
18th -The Kitchen installed.
16th - The fixing chippies started and tilers start
12th - Real stair case installed
11th - temporary stair case removed
8th - Dry wall completed
4th - Dry wall started
3rd - Insulation installed
May 2009
21st - Tilers and guttering finished
19th - Air con, Sound and visual, ducted vac, and alarm installed
15th - Electrical started
6th - Rendering 1/2 painted.
April 2009
29th - sarking laid for roof tiles
21st - Fascia and Gutter arrived
17th - Rendering finished
15th - Rendering began
4th - Brick inspection with SS
March 2009
27th March - Kookaburra pools go bust
16th March - Plumbing started
5th March - Scaffolding is erected
2nd March - Brick work continues
February 2009
28th - We sign the contract for Narellan Pools
27th - More brick laying
25th - Brickies begin laying bricks
18th - BRICKS ARRIVE!
13th - Safety stairs installed in side
11th - Goodies for brick laying arrives
10th - Frame Completed.
9th - Windows put in.
5th - Frame started.
1st - Storm water and surface drainage complete.
January 2009
31st - Plumbing finished
30th - Frames Delivered and Plumbing continued.
28th - Progress payment #1 PAID!
23rd - Slab Poured.
22nd -Site prep finished.
20th - Steal Delivered.
19th - Waffle Pods delivered.
17th - Slab formed and plumbing started.
13th - Site works resume.
1st - We moved for the second time .
December 2008
20th - We Met our SS Mark.
13th - surveyor returns and repegs site.
8th - Site establishment.
11th - Site excavation.
November 2008
7th - Our file handed over to the Construction Planning and Programming department.
5th - Building agreement SIGNED!
October 2008
4th - Peg survey done.
September 2008
25th - DA approved.
12th -Studio M visit to choose our goodies for the house
July 2008 2008
29th - Plans go to council.
18th - Tender C delivered
17th - Soil tests taken
6th - Wendy from head office contacted us.
June 2008
30th - Met Bob and Renaye at Goulburn and chose the Regent Grande.
May 2008
14th - Beechwood goes bust!.
April 2008
12th - We moved to Yass
24th - Settlement day of Gungahlin house.
29th - Neighbour consultation ended.
March 2008
7th - Told by Beechwood we were off to council
September 2007
23rd - Markings for Beechwood house on land
19th - Exchanged on Land
14th - Our Gungahlin house is on the market!
August 2007
25th - We Bought our land!
2 comments:
Lovely balustrade detail guys. There's something about the stairs going in, that makes us all feel that much closer to the END !!! They're gonna be beautiful.
Lovely scrolly bit on the rails. I love that look. not too over the top but just a bit prettier and sassier than standard rail. :)