Thursday, 11 June 2009
Planned Activities for the Next Week...
THIS WEEK:
Tomorrow the internal staircase will be installed.
Saturday the waterproofing will happen in the wet areas.
NEXT WEEK:
Monday - Fitout Carpenter will commence work on the internals (architraves, door frames, doors, etc).
Thursday - Kitchen gets installed - YAY!
Also, our SS told me tonight that Head Office have told him our house needs to be completed and handed over by 30Jul09 - that only 6-7 weeks away!! We'll see...I bet it doesn't happen.
I am sure more will happen, I can't remember it all!
JB & Taz
Tomorrow the internal staircase will be installed.
Saturday the waterproofing will happen in the wet areas.
NEXT WEEK:
Monday - Fitout Carpenter will commence work on the internals (architraves, door frames, doors, etc).
Thursday - Kitchen gets installed - YAY!
Also, our SS told me tonight that Head Office have told him our house needs to be completed and handed over by 30Jul09 - that only 6-7 weeks away!! We'll see...I bet it doesn't happen.
I am sure more will happen, I can't remember it all!
JB & Taz