Thursday 30 April 2009

The Schedule for the coming weeks...

Tonight I spoke with our Site Manager, here is the plan for the next 2-3 weeks:

  • Friday (tomorrow) - Roof Tiling on Level 1 continues...
  • Friday (tomorrow) - Fascia & Gutter on Ground Floor and Garage to be done.
  • Monday (4 May) - Roof Tiling on Ground Floor occurs. Bricklayers return to complete/fix brickwork.
  • Tuesday (5th May) - Roof Tiling finishes. Brickies continue.
  • Wed or Thu (6/7 May) - Carpenter returns to complete the Ceiling Bulkheads.
  • Wed or Thu (6/7 May) - Painter arrives to apply the acrylic membrane to the render on the facade.
  • WEEK from Monday (11 May) - Electrician, Sentinal Alarms and Harvey Norman Air Con arrive to do their stuff...
  • WEEK from Monday (18 May) - Gyprocking can start...

Now, once the Gyprocking is completed the 'usual' time to handover is appx 6-7 weeks - this means our approx. handover date is around:

10 July 2009 ! ! ! :-)

to coincide with the arrival of the Tax Bill :-(

No comments: