Thursday, 10 December 2009
Subscribe to:
Post Comments (Atom)
Nov 2009
17th- concreting began out the back
3rd - pool coping, Fence ( pool and one side) and block wall all finished
Oct 2009
7th - the pool began
Aug 2009
15th - We moved in
14th - Hand over
10th - sentinal installed Music hub, ducted Vac, phone points alarms Ect
6th - Oven, dishwasher, cook top, range hood installed
July 2009
25th - Front received a new coat of applied finish
23rd - We met with Mr L our new Site supervisor.
17th - Electrical fit off, shower screens and mirrors installed
14th - Steps poured
10th -Internal painting finished, concrete for porch slab formed up
6th - Internal paining commenced
4th - Cornice FINALLY started & kitchen bulk heads installed.
1st -iron work erected.
June 2009
20th - Tiles started
18th -The Kitchen installed.
16th - The fixing chippies started and tilers start
12th - Real stair case installed
11th - temporary stair case removed
8th - Dry wall completed
4th - Dry wall started
3rd - Insulation installed
May 2009
21st - Tilers and guttering finished
19th - Air con, Sound and visual, ducted vac, and alarm installed
15th - Electrical started
6th - Rendering 1/2 painted.
April 2009
29th - sarking laid for roof tiles
21st - Fascia and Gutter arrived
17th - Rendering finished
15th - Rendering began
4th - Brick inspection with SS
March 2009
27th March - Kookaburra pools go bust
16th March - Plumbing started
5th March - Scaffolding is erected
2nd March - Brick work continues
February 2009
28th - We sign the contract for Narellan Pools
27th - More brick laying
25th - Brickies begin laying bricks
18th - BRICKS ARRIVE!
13th - Safety stairs installed in side
11th - Goodies for brick laying arrives
10th - Frame Completed.
9th - Windows put in.
5th - Frame started.
1st - Storm water and surface drainage complete.
January 2009
31st - Plumbing finished
30th - Frames Delivered and Plumbing continued.
28th - Progress payment #1 PAID!
23rd - Slab Poured.
22nd -Site prep finished.
20th - Steal Delivered.
19th - Waffle Pods delivered.
17th - Slab formed and plumbing started.
13th - Site works resume.
1st - We moved for the second time .
December 2008
20th - We Met our SS Mark.
13th - surveyor returns and repegs site.
8th - Site establishment.
11th - Site excavation.
November 2008
7th - Our file handed over to the Construction Planning and Programming department.
5th - Building agreement SIGNED!
October 2008
4th - Peg survey done.
September 2008
25th - DA approved.
12th -Studio M visit to choose our goodies for the house
July 2008 2008
29th - Plans go to council.
18th - Tender C delivered
17th - Soil tests taken
6th - Wendy from head office contacted us.
June 2008
30th - Met Bob and Renaye at Goulburn and chose the Regent Grande.
May 2008
14th - Beechwood goes bust!.
April 2008
12th - We moved to Yass
24th - Settlement day of Gungahlin house.
29th - Neighbour consultation ended.
March 2008
7th - Told by Beechwood we were off to council
September 2007
23rd - Markings for Beechwood house on land
19th - Exchanged on Land
14th - Our Gungahlin house is on the market!
August 2007
25th - We Bought our land!
1 comment:
I'm the sort of guy who loves to seek fresh things. Presently I'm building my personalized pv panels. I'm making it all alone without the help of my men. I am utilizing the net as the only path to acheive that. I ran across a truly brilliant website that explains how to make pv panels and wind generators. The site explains all the steps involved in photovoltaic panel building.
I am not sure bout how precise the info given there iz. If some guys over here who had xp with these things can have a peak and give your feedback in the site it will be grand and I would extremely treasure it, cauze I really passion [URL=http://solar-panel-construction.com/useful-articles]solar panel construction[/URL].
Tnx for reading this. You people rock.
Post a Comment